Complete the Go-Live Stage
Use Playbook stage Go-Live to run the live cutover window from the brief and execution command center, then close with an executive readiness summary for stabilization handoff.
Where: Mission Control → W.A.T. Implementations → Implementation Playbook → Go-Live
Route: /missioncontrol/implementations/playbook?phase=beginning_balance_load_go_live
Balance-forward scope should already be decided in Complete the Beginning Balance Decisions stage. Process context: Stage 9: Go-Live.
Steps in this stage
| Step | Title | Primary control |
|---|---|---|
| 1 | Go-live brief | Open command center / Next |
| 2 | Execution command center | Open readiness summary / board Refresh |
| 3 | Executive readiness summary | Complete Go-Live |
Footer can show progress such as balances selected, completed/total on the board, and remaining/blocker counts. The right Required items list shows these three flow steps.
Step 1: Go-live brief
- Align the live-window plan, ownership, and expectations with the team.
- Review recommended rules and common interfacing approaches when shown (for example controlled batch-posting vs traditional full-green-light).
- Confirm selected balances for go-live (count appears in the footer when available).
- Click Open command center (or Next).
Step 2: Execution command center
- Work the execution board populated from Stage 7 selections. The board is empty until Beginning Balance Decisions is finalized.
- Use linked actions with Refresh / Open Company Tracker as needed.
- Update completion as each balance/prereq finishes; watch remaining count.
- When the board work for this window is done (or ready for leadership review), click Open readiness summary.
Step 3: Executive readiness summary
- Review the executive readiness summary for stabilization handoff (Ready for stabilization handoff vs not ready, per product copy).
- Resolve remaining items/blockers if the final CTA is disabled.
- Click Complete Go-Live.
Continue with Complete the Stabilization stage (?phase=stabilization).