Complete the Integrations Stage

Use Playbook stage Integrations to capture connected systems, manage setup/testing checklist items, and sync those items into Company Tracker milestones and actions.

Where: Mission Control → W.A.T. ImplementationsImplementation PlaybookIntegrations
Route: /missioncontrol/implementations/playbook (stage Integrations)


Steps in this stage

StepTitleWhat you do
1Why integrations matterReview coordination guidance; Next marks reviewed
2Track integrations and setup itemsAdd integrations and checklist items under each
3Review and sync milestone actionsSync checklist work into Company Tracker; finish with Complete integrations

Step 1 — Why integrations matter

  1. Review what the stage covers, expectations, and coordination checkpoints.
  2. Click Next.

Step 2 — Track integrations and setup items

  1. Open the starter list accordion and add known integrations (click a name; already-added rows show as Added …).
  2. Or under Add custom integration, enter category + integration name and click Add.
  3. Under Tracked integrations, expand each integration.
  4. Add setup/testing checklist items for that integration (empty state: No checklist items yet.).
  5. Delete an integration only if it should not be tracked (trash on the row).
  6. Click Next when the tracker reflects the real integration set.

Checklist items here are the source used to generate milestones/actions in Step 3.


Step 3 — Review and sync milestone actions

  1. Review the sync summary (counts of items ready to push).
  2. Click Sync (Syncing... while running) to create/update Company Tracker milestones and actions from selected integration checklist items.
  3. Use Refresh after you change linked work in Company Tracker.
  4. Click Complete integrations when the sync plan is accepted.

Continue with Complete the Testing & Training stage. Day-to-day action execution stays in Manage companies, milestones, and actions.