Initializing Material Order Confirmations
IN Material Order Confirm Init initializes material order confirmations so you can confirm orders quickly. You can also confirm manually on IN Material Order Confirmation (File → Initialize Confirmations from that form); Confirm Init is the faster multi-line path.
Update builds the confirmation batch and clears confirmed items from the grid — it does not post. Post with File → Process Batch. Review or edit batch lines on IN Material Order Confirmation before posting.
Before you start
- Materials are already on the material order and were pulled for the job (same lifecycle as Confirming IN Material Orders).
- Prefer Confirm Init for multi-item orders; use Confirmation for single-line or after-init review.
Steps
- Open IN Material Order Confirm Init (or reach it from Confirmation via File → Initialize Confirmations).
- Enter the confirmation Date and Material Order. All items on the order display in the grid.
- Optionally check Confirm the 'Remaining Units' for all Items to fill Confirm This Time with remaining units for every item (Remaining defaults to 0.00). Field defs: that default is remaining units less any remaining-unit changes already in the current batch.
- Edit Confirm This Time if needed. Negative values return units to stock.
- Optionally check Include Items where 'Confirm This Time' equals zero so zero-confirm lines stay in the batch (otherwise they are omitted).
- Review Remaining. If remaining units were initialized, it defaults to 0.00; otherwise Ordered − Confirmed To Date − Confirm This Time. Override is allowed — the system does not recalculate Confirm This Time, and overrides can leave negative remaining and understate committed costs and units.
- Click Update to create/add to the confirmation batch. Confirmed items clear from the grid.
- Repeat for each additional material order — each Update adds to the same existing batch.
- Optionally open IN Material Order Confirmation to review/edit sequences.
- File → Process Batch → validate → preview reports → post.
Key fields
| Field | Behavior |
|---|---|
| Date | Confirmation date for this material order |
| Material Order | Order to confirm |
| Confirm the Remaining Units for all Items | Fills Confirm This Time; sets Remaining to 0.00 |
| Include Items Where Confirm This Time Equals Zero | Keep zero-confirm lines in the batch |
| Confirm This Time | Units confirming now; negative returns to stock |
| Remaining | Override does not recalc Confirm This Time — can understate commitment |
Hard rules
- Zero Confirm This Time lines are excluded unless the include-zero checkbox is on.
- Overriding Remaining without adjusting Confirm This Time can understate committed costs and units.
- One MO per pass; Update clears the grid; more MOs join the same batch until Process Batch.
- Update ≠ post.
Notes
- Related: Confirming IN Material Orders, IN Material Order Entry, IN Material Order Close, IN Add Transaction to Batch, IN Material Copy.