JB Release Retainage
JB Release Retainage releases retainage that was withheld on previously interfaced billings so it can be included on a current billing. Choose Contract (contract-level release; fills every item) or Item (per contract-item grid). Open it from JB Programs under Billing → Retainage (not the Progress Bill Retainage Totals form).
Item retainage % on JB Progress Billing and maximum retention setup are separate topics (Progress Bill Retainage Totals / Applying Maximum Retention).
Before you start
- A bill exists that still has open retainage available to release (typically after prior bills were interfaced).
- Prefer an open bill month. Closed-month (or month closed in subledgers) bills show a warning and disable entry fields — create a new bill in an open month (even with zero bill amounts), then release retainage on that bill.
- Reverse Previously Released Retainage is enabled only for Active bills. You cannot reverse retainage on a closed-month or already-interfaced bill except by releasing on a new open-month bill.
- Know whether AR Company Parameters Release Retainage to Current A/R is checked: if checked, available retainage includes amounts on released-retainage billings; if not, those amounts are excluded.
Release by contract
- Open JB Release Retainage.
- Enter Bill Month and Bill Number (open retainage appears under Release by Contract).
- Select Contract.
- Enter one of % Released This Bill, Amount Released This Bill, or Net Retainage This Bill — changing one recalculates the others. Overriding Amount recalculates %; overriding Net Retainage recalculates both % and Amount.
- Click Update. The system applies the release across each item in the grid.
- Run JB Batch Process so AR is updated (see JB Interface for the broader interface path).
Release by item
- Enter Bill Month and Bill Number.
- Select Item.
- On each grid row, enter % Released or Amount Released, then save the item. Contract-level totals update from the item rows.
- Run JB Batch Process to update AR.
Reverse previously released retainage
- Check Reverse Previously Released Retainage on an Active bill only.
- Enter % fields as a positive value; enter Amount fields as a negative value.
Totals (About help)
- Total Net Retainage available to release = Previous Net Retainage (open retainage) + This Bill Net Retainage.
- Field labels vary slightly across help pages (% Released This Bill / Amt Released / Net Retainage This Bill) — same three contract fields.
Hard rules
- Closed-month billing: all (or all remaining) fields disabled; use a new open-month bill instead.
- Contract Update writes every item; item save updates contract totals.
- Related: JB Progress Billing, JB Bill Initialization, JB Interface, AR Company Parameters.