Managing JC Change Orders
JC Change Orders posts approved change orders to existing jobs. Posting updates current contract amounts and/or current phase estimates. It does not change original contract amounts or original phase-estimate amounts.
There are three levels: change-order header (job / contract, completion date, approval), change-order items (contract items, units, billable dollars), and phase / cost type detail (estimated hours, units, unit cost, cost).
Before you start
- The job and contract exist. Prefer entering proposed / pending COs in Project Management when PM is licensed (pending detail lives only in PM), then interface approved COs to JC (and SL when applicable).
- Only approved changes should be posted directly in JC Change Orders.
- Know whether the CO also affects a subcontract (needs Subcontract Change Order Entry as well).
- You have permission to post JC change orders.
Steps
- Open JC Change Orders (or interface the approved CO from PM).
- Enter the change-order header: job / contract, description, completion-date impact, and approval month as required.
- Add Change Order Items tied to contract items (existing or new). If the contract item does not exist, Vista opens JC Contract Items so you can add it.
- On phase / cost type detail, enter estimated Hours / Units / Unit Cost / Cost for affected phases. New phases can be created here even when the job's phases are locked (similar to Original Estimates for estimate-only adds). New phases cross-reference the CO item's contract item.
- Review Revenue / Cost / Profit / Markup displays on the form as you enter items and phase detail.
- Save / post per your batch process. If the job uses roles and the CO added phases, run File > Job Phase Roles Initialize so new phases get role assignments.
Notes
- If PM is licensed, enter and track COs in PM, then interface approved COs to JC. PM and JC store details differently; pending details exist only in PM.
- Changes that affect a subcontract also require Subcontract Change Order Entry.
- Un-interface guidance in legacy flows often means deleting the JC side when reversing an incorrect interface; follow your PM/JC interface procedures carefully.
- Related: Managing JC Original Estimates, JC Contracts, JC Jobs, JC Job Phases.