Managing PM Cost Projections
PM Cost Projections uses projection codes (layouts) and monthly projection entry. Document types/status IDs control whether pending change orders appear or calculate in projections.
Before you start
- Project phases and cost types exist.
- Decide the projection layout (phases and cost types, phase, cost type, contract item, or copy from another job).
Steps
Projection codes
- Create PM Projection Codes (task option) and choose a layout type.
- Optionally copy codes from another job.
- Reinitialize codes when new phases or cost types are added mid-project.
Monthly projections
- Open PM Cost Projection.
- Set the projection date to the month-ending date.
- Enter projected costs for each row.
- Process/post per your batch procedures.
Pending change orders in projections
- In PM Document Types, check Include in cost projections for pending change orders if they should appear.
- In PM Status IDs, choose display in projections or display and calculate in projections as needed.
Notes
- Reinitialize projection codes after phase/cost-type structure changes.