Managing PM Cost Projections
PM Cost Projections enters cost projections for a job/project in a batch (one project per batch). The system can calculate values, you can plug your own, or both. Flow: create batch → enter projections → review and post → view posted history.
Before you start
- Projection codes are set up on the job (PM Projection Codes).
- Project is interfaced to Job Cost (only interfaced projects appear).
- Configure File → Projection Options (opens on form open if that option is checked). Projection Method = Actual Cost or Actual + Committed Cost (drives Editor columns and buyout math).
- Plug columns (Percent Complete, Over/Under, Remaining) appear only if enabled on PM Company Parameters → Projections → Columns for Entry.
- Projection Detail tab / Initialize Worksheet Detail only if Activate Projection Detail Feature is on (help cites PM or JC Company Parameters → Projections inconsistently — check both if the tab is missing).
Steps
1. Create the batch
- Open PM Cost Projections.
- File → Projection Options and set options.
- Enter Projection Date (month the batch posts to; F4 lists existing batches; one user per batch) and Project.
- Choose how rows populate → Initialize. Optionally Initialize Worksheet Detail if detail is activated.
- Codes appear on the Grid; phases/cost types on the Phase/Cost Type tab. If rows are missing, check Options (e.g. Show Linked Cost Types) and assignment.
- Optional layouts via PM Projection Layouts.
Multi-open same month: allowed only if PM Company Parameters → Projections → Allow projects in multiple open projections in the same month is checked.
2. Enter projections
- Filter/sort the Grid (e.g. by exposure).
- Plug Percent Complete, Over/Under, Projected Final, or Remaining (hours, units, cost, unit cost, production) on the Grid, Phase/Cost Type tab, or Cost Projection Editor (double-click). Changes sync across views immediately.
- Grid plug applies across all phases/cost types on that projection code. Spread follows PM Company Parameters → Projections → Spread Option (Prorated = weighted average of phase/CT % complete; Defined at projection code = Spread % on PM Projection Codes).
- Plugging a primary cost type updates linked types by the same percent.
- Check Buyout when commitments are complete (subs, POs, material orders) so finals calculate from the projection method. Checking it on a code checks associated phases/CTs and linked types. Blue row = plugged value ≠ calculated buyout. Yellow = phase/CT has a plug that highlights the code on the Grid.
- Optional Projection Detail on the Editor; Future Change Orders shows PCO/ACO items not yet interfaced to JC.
Refresh vs new codes: File → Refresh Data pulls costs posted to the batch month or prior months, but does not update Project Cost, add new projection codes, or add new phases/CTs. For new codes/assignments: create a new batch, or use Update Projections. Unassigned phase/CT label → Task → Assign Phase. Still missing after assign → Tasks → Clear Projections, fix PM Projection Codes, create a new batch.
3. Review and post
- Review Grid totals.
- Submit Projection (close without it: Yes = submit; No = save for later).
- JC Batch Process / PM Batch Process opens → Validate → print/preview audit reports (attach to HQ Batch Control if JC Company Parameters → Info → Attach Batch Reports to HQ Batch Control is on).
- Confirm Posting Date → Post.
4. View posted projections
PM Work Center → Items → PM Cost Projection History (only on standard work centers added after 6.8.x, or if inquiry PMCostProjectionHistory was added). Select Project → double-click a batch.
Pending change orders in projections
- On PM Document Types, check Include in Cost Projections for PCO types that should appear.
- On PM Status IDs, set Projections Option to Display or Display & Calculate as needed.
Notes
- Clear an open batch: Tasks → Clear Projection(s) (help uses both singular and plural) — clears entries for that date/job and deletes the batch.
- If phases/cost types are missing from the grid, see Why Phases or Cost Types Are Missing in Cost Projections (PM uses File → Cost Projection Options; checks align with JC).
- Related: PM Cost Projection Options / Editor / Layouts, PM Projection Codes / Assign / Copy, PM/JC Batch Process, HQ Batch Control, PM Company Parameters, JC Company Parameters.