Managing PM Pending Change Orders
PM Pending Change Orders creates and maintains pending/potential change orders (PCOs) before they become approved change orders. A PCO records a potential work change with pricing against estimates, commitments, and contract items. After entry, approve with PM Approve PCOs, then interface to Job Cost / SL / PO / IN / MS with PM Interface.
Also: add items, generate a CO document, create a COR, copy a PCO, create a transmittal.
Before you start
- Project exists. Soft/hard-closed projects show status in red; add/edit only if JC Company Parameters allow posting to those jobs.
- PCO Type from PM Document Types (defaults for Estimate / SL / PO / Contract / Pricing Method).
- Auto-numbering on PM Projects → Info → Auto-Generate Pending Change Orders (by Project, or Project and Type). Trailing letters ignored; trailing digits count.
- Header Status defaults from PM Company Parameters Default Beginning Status. Final statuses on PM Status IDs.
- Responsible Person = contacts of Our Firm only.
- Phases/cost types on PM Project Phases; hours only if JC Cost Type tracks hours. Add-ons from PM Project Add-Ons; markups from PM Projects Markups. ROM required (0.00 if none) — informational.
Steps — create and maintain
- Open PM Pending Change Orders. Enter Project, PCO Type, PCO (
+or New Record). Description (60), Details, Date (today), Status, Priority (default Medium), Reason, Reference, Responsible Person. - Check impacts: Estimate, SL, PO, Contract. Pricing Method filters unit columns (Lump Sum hides unit/unit-cost).
- Add PCO items (
+, up to 10 chars): description, status, Budget # (reference only), Force Phase, Change in Days, Contract Item (required before approve — can wait until Approve PCOs), dates, RFI links, Initiated By. - With Estimate checked: enter phase/cost type estimate lines (UM, units, hours, costs, ECM, Interface, Active, Ins Code, Bill Flag, unit flags, notes). Phase must be active on the JC job.
- With SL/PO checked: Vendor; attach existing approved (or approved+interfaced) SL/PO or create new. New SL creates a subcontract on save even before PCO approval — changing the SL # after save creates another subcontract, it does not renumber. Attach existing SubCO/POCO only on a new detail line with blank Phase/Cost Type (use Create → Subcontract/PO Change Order).
- With Contract checked: Fixed Amount or calculated Pending Amount; UM mismatch warns that only dollars update JC. Change in Days adds to PM Contracts current days on approve.
- Markups and add-ons as needed. Optional Add PCO Items, generate document, create COR, copy PCO, mass-assign contract items.
Unchecking Estimate deletes estimate lines (prompt). Unchecking SL/PO hides columns and clears values but does not delete already-created subcontract/material detail.
Approve to ACO
- From a COR: Tasks → Approve PCOs (loads that COR’s PCOs). Or on this form’s Grid tab: multi-select PCOs, then approve.
- On PM Approve PCOs: select PCO(s), ACO (
+or existing), optional approve related SubCOs/POCOs, optional CCO, check Approve per item, set Approved Amount, Approve. - Estimates flow to ACO Estimate Detail, then to JC Change Order Phase Detail at PM Interface. Many item fields disable after the item is approved.
Hard rules
- Do not set Default Final Status until after printing the PM Pending Change Order Form report — PCOs in that status are excluded from the report.
- Active checked = phase/CT updates JC immediately and can collect cost; unchecked = pending until approve + interface. Force Phase runs only at interface.
- Material cost type + PO → PM Material Detail; subcontract cost type + SL → PM Subcontract Detail.
- Cannot remove a linked POCO/SCO from a saved line — delete the line (unapprove first if already approved).
- ROM from RFI/issue does not fill header ROM; it defaults item contract amount. Create those PCOs with PM Create PCO.
- Document type Include in Cost Projections + status Projections Option control whether PCOs display/calculate in cost projections.
Notes
- Related: Managing PM Change Order Requests, Managing PM Approved Change Orders, PM Approve PCOs, PM Interface, PM Document Types, PM Status IDs, PM Company Parameters, PM Projects / Phases / Add-Ons, PCO Setup Options.