Managing PM Template Phases
PM Template Phases builds templates of phases and cost types that are common for a project type (for example OFFICE, HOUSING, STREET). After setup, roll the template into a project with PM Copy Template, then tailor phases and cost types in PM Project Phases.
Help lives under Projects and Contracts → Projects (not Setup/Maintenance). There is no numbered create procedure on the form; the linked “About Adding Template Phases to a Project” topic 404s in Trimble Help.
Before you start
- Phases exist in JC Phases (field defs may say JC Phases Maintenance).
- Cost types on a template phase must already be defined for that phase in JC Phases.
- Standard item codes come from JC Std Item Codes.
- Destination project already exists in PM Projects before you use PM Copy Template.
Steps — create or maintain a template
- Open PM Template Phases.
- Enter Template (up to 10 characters — unique name for the project type) and Description (up to 30).
- On Info and/or Grid, add each typical Phase (enter or F4). Phase Description defaults from JC Phases (editable, up to 30).
- Optionally enter Contract Item (up to 16 digits) and/or Std Item Code. On roll-in, the phase links to that contract item; if the item is missing on the destination contract, roll-in creates it (description from the phase; if several phases share the item, the first phase’s description wins).
- On Cost Types, cost types from JC Phases for that phase are added automatically. Delete extras, or re-add a deleted one by typing its cost-type number.
- Save. Repeat for other templates.
Estimates are not on the template. Estimated units, hours, dollars, and contract amounts are set later in PM Project Phases and PM Contract Items.
Steps — apply to a project (PM Copy Template)
- Open PM Copy Template.
- Select the template and an existing PM project.
- Copy / roll in. First copy sets up data in PM Projects and PM Contracts. Additional templates can be rolled into the same project — new phases and contract items are added; duplicate phases are skipped (same phase on multiple templates appears once).
- Tailor phases, cost types, and estimates in PM Project Phases (and contract amounts in PM Contract Items).
Contract-item fallback on roll-in
- No contract item, but a standard item code → standard item code becomes the contract item (description from the std item).
- Neither contract item nor standard item code → phase is assigned to contract item #1.
Notes
- Related: PM Copy Template, PM Project Phases, PM Contract Items, PM Projects, JC Phases, JC Std Item Codes.