PM Copy Template
PM Copy Template adds phases and cost types from a PM Template Phases template into an existing project. The destination project must already exist in PM Projects. Estimated units, hours, dollars, and contract amounts are not on templates — enter them after the roll-in in PM Project Phases and PM Contract Items.
Before you start
- Template exists in PM Template Phases.
- Project exists in PM Projects.
- Know how missing contract items / JC standard item codes should resolve (contract region + JC Company Parameters Add Standard Item Code to Database if Not on File).
Steps
- Open PM Copy Template.
- Enter the Template (from PM Template Phases).
- Enter the Project.
- Click Copy.
- Review phases in PM Project Phases and enter estimates / contract amounts as needed.
What is copied
- All template phases and cost types into PM Project Phases, with standard item codes assigned to the template’s contract item.
- Missing contract items are created on the contract (PM Contracts).
- Phases/cost types missing from JC Phases still copy, forced to UM = LS, Bill Flag = C, Item Unit / Phase Unit = N.
- No contract item and no standard item code → phase assigned to contract item #1 (procedure: item description = project description, UM = LS).
- Standard item code valid for the contract’s region and no contract item → that code becomes the contract item (description/UM from JC Standard Item Codes).
- Standard item code not on file for the region:
- Add Standard Item Code… checked: add to JCSI, create contract items, phases use that code as the contract item.
- Unchecked: clear the standard item code; assign phase to contract item #1.
- Procedure only: a subcontract cost type on any phase adds a PM Subcontract Detail row.
- Multiple templates: first copy builds phase/contract-item data on the existing project; later roll-ins add new phases (skip duplicates) and new contract items.
What is not copied
- Estimated units, hours, dollars, and contract amounts.
- If a phase already sits on a contract item and a standard item code is also specified, the item code is not copied to the contract (phase/cost types still add).
- Procedure: if the contract has no region, the standard item code is unused; description comes from the phase and UM is LS.
Notes
- The form’s in-page “About Adding Template Phases to a Project” link may 404 (path without
_1); use the About Project Setup sidebar topic. - Related: Managing PM Template Phases, Managing PM Project Phases, PM Copy Project, PM Contracts / Contract Items, JC Phases, JC Company Parameters, JC Standard Item Codes.