EM Process Cost Allocations charges overhead or other indirect costs to equipment from parameters on EM Allocation Codes. It is not required EM processing — use it only to post additional overhead. Each run creates cost-adjustment lines (EM Type A) in an open EM Cost Adjustments batch. Edit and post that batch before you purge it.

Flow: set up allocation codes → process here → review/post in EM Cost Adjustments.

Before you start​

  • Allocation codes exist (code 0–255) with Basis, Date Options, amount/rate, and post options (Cost Code, Cost Type, Debit Account, Credit Account required). If Debit Account is blank, GL comes from the EM department for the cost code and cost type.
  • Equipment / Departments / Categories to Allocate is set to All, Assigned (tabs filled, often via EM Allocation Initialize), or Prompt for… (you enter them when processing).
  • Basis Cost Types (Costs basis) or Basis Revenue Codes (Hours / Revenue basis) are listed on the code. For Cost basis with blank Cost Code/Type on the code, amounts post to the same cost code/type as the basis; basis cost types must appear on the Allocated Cost Types tab.
  • Interface all costs the allocation is based on before you run Process. Missing or wrong basis costs mean: delete the Type A lines in Cost Adjustments, fix/interface the costs, then run the allocation again.
  • Re-running in the same month does not back out prior allocations — each Process calculates and posts additional costs.

Steps​

  1. Open EM Process Cost Allocations.
  2. Enter Allocation Date (date on all transactions in the batch; becomes Actual date in EM Cost Detail).
  3. Optionally check Reversal so every line is flagged Auto Reverse (1); unchecked = Regular (0). You can change reversal status later in EM Cost Adjustments. Auto-reverse lines are included when initializing reversals in EM Initialize Reversals.
  4. Enter Allocation Code. The form shows the code’s setup (equipment, departments, categories, basis cost types/revenue codes, amount or rate, and post-to cost code). Prompts depend on that setup.
  5. If the code uses Prompt for Equipment / Department / Categories, enter those values (F4).
  6. If Date Options is By Date Range, enter Begin Date and End Date. Those fields are unavailable when the code uses a specific month.
  7. Confirm or enter Amount to Allocate and/or Rate to Allocate (defaults from the code; 0.00 / .000000 on the code forces entry here). Positive or negative (example: refund of a prior allocation = negative). For revenue or costs basis, rate is a percent of the basis; for hours, rate is dollars per hour.
  8. Select Show Basis to see the basis amount used (for Costs: total costs posted for the specified equipment, departments, and categories).
  9. Select Process. On success, allocations are added to the Cost Adjustments batch for edit. Close and process additional codes as needed. If Process fails, the message lists the reason(s).
  10. Open EM Cost Adjustments, review Type A lines, then validate and post the batch.

Allocation bases (on the code)​

BasisUses
CostsTotal dollars posted to basis cost types
HoursRevenue/usage hours (time or work units × hours per unit for each basis revenue code)
RevenueTotal revenue/usage dollars on basis revenue codes
VariableA variable on EM Equipment (standard examples: PurchasePrice, CurrentAppraisal, ReplCost, LeasePayment, or custom fields)

Accumulated dollars, hours, or revenue follow Date Options: By Month or By Date Range.

Amount/rate can be a flat Allocation Amount, Allocation Rate, or an Equipment Amount/Rate Column from a custom field on EM Equipment (VA Custom Fields Wizard on EM Equipment). A bDollar custom field used as a rate is converted (example: 250.00 ÷ 100 hours = 2.5 × 100 = 250.00), not added as a flat dollar.

Notes​