SL Change Order Entry
SL Change Order Entry changes current contract amounts on regular or add-on subcontract items, or adds new change-order items. Posted changes do not rewrite Original units or costs — Current becomes original plus change order. Committed cost picks up the CO units/dollars in the month of the CO Date.
Help’s linked primary procedure only covers adding a new item number; batch validate/post follows the normal SL batch path (not detailed on these pages).
Before you start
- Subcontract already exists (see Entering Subcontracts).
- New or existing SL batch (Sequence # = New on a new batch; system assigns). On an existing batch, enter the sequence or New. File → Add Transaction pulls an existing CO into the batch.
- Know Sub CO#, Approved CO (owner CO #), and the unit/cost deltas.
Steps — change an existing item
- Open SL Change Order Entry and accept or enter Sequence #.
- Action defaults to A (Add) and is locked on new rows. For previously posted COs: C (Change) or D (Delete from related module files). Toolbar / Records delete only removes the batch line.
- Enter Subcontract and Item# (F4). Both are disabled when editing or deleting a previously posted CO.
- Enter Sub CO# (up to 6 digits — drives which prior COs appear on the SL Change Order report line for previously authorized net change; print includes CO numbers less than this number), optional Approved CO, Date (defaults today; month when units/dollars hit committed cost), Description (60).
- Enter Change to Current:
- Units — delta to original units (negative to reduce, e.g.
–150.000). - Unit Cost — enabled only if the item was added on the fly via SL Add Item and UM is not LS; otherwise disabled.
- Total Cost (LS only) — delta to original total cost. For add-ons, use Add-on Amount (delta to original add-on amount; if original add-on is negative, a negative change makes it more negative).
- Units — delta to original units (negative to reduce, e.g.
- Save. Lower calculated fields show results after save.
- Validate and post the SL batch.
On post, PM Subcontract Detail (PMSL) updates for the CO when the SL batch month and transaction are found in PMSL.
Steps — add a new change-order item
- Enter an Item# that does not exist (F4 lists existing). Warning that the item does not exist → Close → Yes to add → SL Add Item opens.
- In SL Add Item enter job/phase/cost type, UM, GL Account, WC and SM Ret%, supplier, description (same pattern as adding a CO item in SL Subcontract Entry) → Add.
- Item returns to SL Change Order Entry for the cost deltas above.
Add-ons
Percent-of-contract add-ons are not auto-applied when you change regular/CO items on this form. After changing those items, put the add-on in the batch so the add-on change calculates and defaults.
Notes
- Field defs say units/total/add-on amount “affect the original” amounts; the About page says Original is unchanged and Current = original + CO. Treat Current as what updates; Original stays as posted originally.
- Related: Entering Subcontracts, SL Add Item, Add Transaction to Batch, SL Change Order report, PM Subcontract Detail, Posting SL Change Orders in Other Forms, JC/PM Change Orders (related topics in help).